Fair and(1) competition in government procurement around the world is good business and good public policy. Competitive pricing, product(2)and performanceimprovements result from competitive practices and help ensure that government authoritiesget the best (3)for the public they serve.
空白(3)處填()
A.help
B.server
C.value
D.policy
您可能感興趣的試卷
- 2009年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2009年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2010年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2010年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2011年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2011年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2012年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師上半年上午試卷
你可能感興趣的試題
Fair and(1) competition in government procurement around the world is good business and good public policy. Competitive pricing, product(2)and performanceimprovements result from competitive practices and help ensure that government authoritiesget the best (3)for the public they serve.
空白(2)處填()
A.recession
B.innovation
C.crisis
D.ability
Fair and(1) competition in government procurement around the world is good business and good public policy. Competitive pricing, product(2)and performanceimprovements result from competitive practices and help ensure that government authoritiesget the best (3)for the public they serve.
空白(1)處填()
A.open
B.continue
C.dependent
D.reliable
Many of the activities performed during the preliminary investigation are still being conducted in(1),but in much greater depth than before. During this phase, the analyst must become fully aware of the (2) and must develop enough knowledge about the (3)and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4)for process and data of current system, the deliverable from this phase also includes the(5)for the proposed system.
空白(5)處填()
A.hardware and software specification
B.system performance specification
C.formal requirements definition
D.generalproblemstatement
Many of the activities performed during the preliminary investigation are still being conducted in(1),but in much greater depth than before. During this phase, the analyst must become fully aware of the (2) and must develop enough knowledge about the (3)and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4)for process and data of current system, the deliverable from this phase also includes the(5)for the proposed system.
空白(4)處填()
A.logicalmodels
B.physicalmodels
C.designmodels
D.implementationmodels
Many of the activities performed during the preliminary investigation are still being conducted in(1),but in much greater depth than before. During this phase, the analyst must become fully aware of the (2) and must develop enough knowledge about the (3)and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4)for process and data of current system, the deliverable from this phase also includes the(5)for the proposed system.
空白(3)處填()
A.hardware environment
B.testingenvironment
C.software environment
D.business environment
最新試題
The TCP protocolis a ()layer protocol.
Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()
空白(2)處填()
空白(4)處填()
You are working on the cost budget for one project. Which of the following is true()
空白(1)處填()
A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives.
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.
Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.