單項選擇題

PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.

A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish


最新試題

空白(1)處填()

題型:單項選擇題

A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives.

題型:單項選擇題

空白(2)處填()

題型:單項選擇題

In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.

題型:單項選擇題

Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.

題型:單項選擇題

空白(2)處填()

題型:單項選擇題

Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

題型:單項選擇題

Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.

題型:單項選擇題

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

題型:單項選擇題

An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

題型:單項選擇題