單項(xiàng)選擇題An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

A.Total float for the activity is 9 days.
B.The early finish date ofthe activity is the end ofthe day on the 14th.
C.The late finish date is the 25th.
D.The activity can be completed in 2 days ifthe resources devoted to it are doubled.


你可能感興趣的試題

2.單項(xiàng)選擇題

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

A.independentresource
B.individualworkload
C.workmilestone
D.workpackage

4.單項(xiàng)選擇題

Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

A.executive IT manager
B.projectmanger
C.change control board
D.projectsponsor

最新試題

There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.

題型:?jiǎn)雾?xiàng)選擇題

空白(4)處填()

題型:?jiǎn)雾?xiàng)選擇題

The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.

題型:?jiǎn)雾?xiàng)選擇題

空白(1)處填()

題型:?jiǎn)雾?xiàng)選擇題

空白(2)處填()

題型:?jiǎn)雾?xiàng)選擇題

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

題型:?jiǎn)雾?xiàng)選擇題

The TCP protocolis a ()layer protocol.

題型:?jiǎn)雾?xiàng)選擇題

空白(3)處填()

題型:?jiǎn)雾?xiàng)選擇題

In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.

題型:?jiǎn)雾?xiàng)選擇題

Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

題型:?jiǎn)雾?xiàng)選擇題