Many of the activities performed during the preliminary investigation are still being conducted in(1),but in much greater depth than before. During this phase, the analyst must become fully aware of the (2) and must develop enough knowledge about the (3)and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4)for process and data of current system, the deliverable from this phase also includes the(5)for the proposed system.
空白(1)處填()
A.analysis phase
B.designphase
C.implementationphase
D.maintenancephase
您可能感興趣的試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專(zhuān)業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專(zhuān)業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專(zhuān)業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專(zhuān)業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專(zhuān)業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專(zhuān)業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2012年計(jì)算機(jī)技術(shù)與軟件專(zhuān)業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
你可能感興趣的試題
The (1) is a general description of the architecture of a workflow management system used by the WFMC, in which the main components and the associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several (2).
空白(2)處填()
A.workflow engines
B.processes
C.workflow threads
D.tasks
The (1) is a general description of the architecture of a workflow management system used by the WFMC, in which the main components and the associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several (2).
空白(1)處填()
A.waterfallmodel
B.workflowreferencemodel
C.evolutionarymodel
D.spiralmodel
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.
空白(3)處填()
A.project scope statement
B.statement of work
C.project management plan
D.projectpolicy
最新試題
The connection between two networks from an intemet is handled by a machine known as a()
The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.
空白(3)處填()
An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
空白(2)處填()
空白(1)處填()
空白(1)處填()
A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives.
空白(3)處填()
空白(2)處填()