單項選擇題

The() defines the phases that connect the beginning of a project to its end.

A.schedule
B.project life cycle
C.temporary
D.milestone


你可能感興趣的試題

1.單項選擇題

()means that every project has a definite beginning and a definite end.

A.Project phase
B.Unique
C.Temporary
D.Closure

2.單項選擇題

() is one of the quality planning outputs.

A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist

3.單項選擇題

The inputs of developing project management plan do not include()

A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes

4.單項選擇題

Which of the following statement related to PMO is not correct?()

A.The specific form, function, and structure of a PMO are dependent upon the needs of the organization that it supports.
B.One of the key features of a PMO is managing shared resources across all projects administered by the PMO.
C.The PMO focuses on the specified project objectives.
D.The PMO optimizes the use of shared organizational resources across all projects.

最新試題

空白(1)處應選擇()

題型:單項選擇題

()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

題型:單項選擇題

()is a category assigned to products or services having the same functional use but different technical characteristics. It is not same as quality.

題型:單項選擇題

The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

題型:單項選擇題

()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.

題型:單項選擇題

() is one of the quality planning outputs.

題型:單項選擇題

Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

題型:單項選擇題

Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

題型:單項選擇題

()means that every project has a definite beginning and a definite end.

題型:單項選擇題

In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.

題型:單項選擇題